A building permit is compulsory for any new construction in Togo, as well as for significant extensions and renovations that touch the structure. Without one, your building is unlawful, and you expose yourself to penalties ranging from a fine to a demolition order.

This guide sets out the official process step by step, the documents required, the real costs to anticipate, and the timescales to expect. Without the administrative jargon.

2025 update: Togo's Directorate of Urban Planning and Architecture (DUA) has partly digitised some steps. Physical submission of files nevertheless remains compulsory. The timescales given reflect conditions in the first half of 2025.

Who needs a building permit?

A building permit is required for:

  • Any new build, whatever its floor area
  • Extensions adding more than 20 m² to an existing building
  • Added storeys
  • Rebuilding after partial or total demolition
  • Certain changes of use (converting a warehouse into housing)

Small ancillary works (boundary walls, lightweight garden sheds) may be exempt, depending on their nature and the rules of the municipality concerned.

The complete file: documents required

What a building permit file must contain in Togo is set by the Urban Planning Code. Here are the documents to gather:

Administrative documents

  • The building permit application form (available from the DUA)
  • A certified copy of the land title
  • A copy of the owner's identity card
  • A certificate that the plot lies within a building zone
  • The receipt for the file charges

Technical documents (to be supplied by an OTOAG-registered architect)

  • Site plan (position of the building on the plot, access, boundaries)
  • Elevations (all 4: north, south, east, west)
  • Sections (at least 2, cross and longitudinal)
  • Floor plans (ground floor plus each upper floor)
  • A specification of the materials and construction methods
  • An outline description of the foundations
  • The registered architect's stamp and signature on every drawing
Important: the architect must be a member of the Togolese Order of Technicians and Architects (OTOAG). Drawings signed by an unregistered technician are rejected by the DUA.

The procedure, step by step

Step 1 · Preparing the file (4 to 8 weeks)

Before filing anything, your drawings must be finalised and signed by a registered architect. This is usually the longest part: allow 3 to 6 weeks for good drawings, including the back and forth of approval with your architect.

Step 2 · Filing the application with the DUA

The complete file is filed in 4 copies with the Directorate of Urban Planning and Architecture, or with the competent municipal department depending on your municipality. You are given a filing receipt. Keep it safe: it is your proof of submission.

Step 3 · Assessment of the application (60 to 90 days)

The statutory assessment period is 2 months for a straightforward building, rising to 3 months for more complex ones or those needing further opinions (fire safety, highways, and so on). In practice, allow 2 to 4 months.

Step Timescale Who
Preparing the drawings 3 – 6 weeks OTOAG-registered architect
Gathering the administrative file 1 – 2 weeks Owner + architect
Filing and registration with the DUA 1 – 3 days DUA / town hall
Assessment of the application 60 – 90 days DUA + departments consulted
Notification of the decision Within the 90 days DUA
TYPICAL TOTAL 3 to 5 months Not applicable

Step 4 · Receiving and displaying the permit

Once the permit is granted, you receive an order signed by the competent authority. That document must be displayed on the site, visible from the public highway, for the whole duration of the works. It is a legal obligation.

The real costs to anticipate

The costs attached to a building permit in Togo come in several parts:

Item Indicative amount (FCFA)
DUA file charges 50 000 – 150 000
Planning taxes (calculated on floor area) 200 000 – 600 000
Architect's fees (drawings + permit) 500 000 – 1 500 000
Sundries (copies, certification, travel) 50 000 – 150 000
Estimated total 800 000 – 2 400 000

These amounts vary significantly with the municipality, the floor area built and the architectural complexity of the project. For a straightforward house in Lomé, the total "permit plus drawings" budget comes in at around 1 to 1.5 million FCFA.

If the application is refused: what to do

An application can be refused for several reasons: failure to meet the neighbourhood's massing rules, exceeding the plot ratio, incomplete drawings, or a plot lying outside a building zone.

Where an application is refused, the DUA must give written reasons. You may then:

  1. Correct the file in line with the comments and file it again
  2. Apply for a waiver of certain planning rules
  3. Lodge an administrative appeal with the DUA
  4. As a last resort, bring the matter before the administrative court

Handling the permit from abroad

If you are in the diaspora, you do not have to be in Lomé to file your application. You can appoint someone you trust through a notarised power of attorney to represent you before the DUA.

Your architect can also handle all the administrative steps on your behalf, as part of their project supervision role. This is the most common arrangement for diaspora clients.

P2G Investments takes on: coordination with the registered architect, monitoring of the permit application, and chasing the DUA, while you stay informed from your country of residence.

What to take away

A building permit is not an optional formality. It is the legal guarantee that your building is compliant, recognised and protected. Allow 3 to 5 months between starting the administrative phase and holding the permit. Begin as soon as your land title is finalised, rather than running it alongside the works.

A project that is administratively sound from the outset spares you years of litigation and gives you a property value that is fully recognised and can be passed on.